Beemer Companies   
 
  HomeServicesProjectsCompany  
 
   
 
   


Bob Ankeny Shoreline Project

Hall Lake in Fairmont, Minnesota

Installed ATV - Snowmobile Trail down 70' embankment to access boat, dock, and lakeshore area. Excavated 12' cut, through upper bulkhead of retaining wall, dragged the walk path to lakeshore for paved trail to prevent any erosion of steep slope. Riprap (installation of large boulders, approximately 2-3'feet diameter) along the slope with geo-textile fabric underneath Riprap System to prevent sub-surface erosion. Installation of oval 8' x 5' x 50' culvert furnished by Contex Industries, Shakopee, Minnesota to prevent accidental slips and falls into 12' cut and aesthetically bring his backyard back to a completed landscaped appearance. Project was pre-approved by the Minnesota Department of Natural Resources and the City of Fairmont, Minnesota.

 

Click Photo to Enlarge

 


Jim's SuperValu

Austin, Minnesota

Jim's SuperValu is a new grocery store located in Austin, Minnesota; Ankeny Builders was the general contractor out of Blue Earth, Minnesota. Beemer Companies performed the mass grading for the five acre site including soil corrections and footing excavation. We excavated approximately 25,000 cubic yards of granular fill to be placed and compacted to bring the site up to final grade. The project needed to be put on the fast track with the building delivery date only a few weeks away. With Beemer Companies capabilities and experience with similar projects there was no doubt we could handle the project schedule put in front of us. With the excellent cooperation between the owner, city, and general contractor the project was completed on time.

 

Click Photo to Enlarge

 

Elm Creek Bio-Engineering Project
Martin County, Minnesota

Riprap sharp bend in Elm Creek to flash point on river bank and use Willow Tree Saplings to stabilize the river bank at flood conditions. Geo-textile matting fabric was dove-tailed 2' below creek bottom. Then 18" - 24" Quartzite Riprap was installed up to the flash point of Elm Creek. To prevent bank erosion from surface water over the top of the bank, a Riprap waterway was created to direct surface water to flow into the creek. This was a joint project with the Martin County Highway Department. Bio-Engineered Willow Sapling mat was supervised and installed by the Martin County Highway Department.

Click Photo to Enlarge

Residential 6" PVC Well
Clear Lake, Iowa

Using existing geological survey maps, bedrock was determined at a depth of 130'. Rock was penetrated 20' to a depth of 150' at which point 6" PVC Casing was set and grouted to surface with Bentonite grout. Rock drilling through the PVC Casing took us into the limestone to a depth of 205' at which point the well was producing 75 gallons per minute. The well was then developed and cleared for installation the pump and pressure system.

Click Photo to Enlarge

Municipal Well
Fairmont, Minnesota

Removed  and installed 10" submersible 75 H.P. pump and replaced 8" drop-pipe column in backup well for the City of Fairmont, Minnesota.

Click Photo to Enlarge

 

 
 

Copyright © 2004 Beemer Well Drilling Inc. All Rights Reserved.

Site Design By
Electra-Sketch Studios